Timeline

The council is committed to working within the timeframes set by government to deliver Local Government Reorganisation (LGR).  

2025

  • data teams set up to support development of proposals 
  • emerging proposals developed and shared 
  • consultation with residents  
  • consultation with staff 
  • final proposals submitted to government (November 2025) 

2026

  • final proposals agreed by government (summer 2026) 
  • transition teams from each authority take shape – focused on workstreams 
  • informal staff engagement through service design 

2027

  • transition teams continue to develop programme for transition 
  • informal and formal engagement in readiness for go live in 2028 

2028 onwards

  • vesting day for new unitary authority (1 April 2028) 
  • structures continue to be developed